On award of a contract and after receipt of all architectural, plumbing and structural drawings pertaining to plumbing installations, We prepare a schedule of drawings which shall contain following details:
This schedule is made to keep track of drawings required and to monitor its status including submission, revision(s) and approval. It may be revised periodically when fresh architectural drawings are issued.
A construction schedule shall be prepared based on the target dates given by the client/consultant.
All efforts shall be made to adhere to this schedule. It will be reviewed weekly and revised if any delays occur due to unforeseen and unavoidable circumstances, keeping in mind the final date of completion.
A Material Proposals’ schedule shall be submitted to the Client / Consultant giving details of materials, manufacturer’s name, technical details etc. Once these are approved, procurement will begin and a “Material procurement schedule” will be submitted.
Total care shall be taken to ensure that the materials that finally arrive at site meet all requirements of specifications and the bill of quantities, for which the store-keeper and site engineer should be responsible.
Adequate workforce shall be deployed at all times to meet the approved construction schedule. The workforce shall be suitably augmented as demanded by actual site conditions.
Site staff will be organised as per an ‘Organisation Chart’ issued at the beginning of the Project. Any revisions to the site organization will be duly recorded and intimated to the Project Managers.
Weekly site meetings shall be attended by a senior member of the contractor’s team. There should be periodic visits by the Executive Management.
Any deviation from approved working drawings made by site instructions by the Client / Consultant shall be indicated in the ‘As Installed’ drawings to be issued at the end of the project. These instructions will have to be formally confirmed before the required changes or deviations are implemented. Time or cost implications, if any, shall be brought to the client’s notice subsequently.
A safety plan shall also be submitted prior to commencement of work. Due care shall be taken as regards all the safety aspects of the works. Relevant PPE (Personal Protective Equipment) shall be used by all personnel working on the installation.
The water distribution system should be thoroughly disinfected before being put to use. The following simple procedures will ensure satisfactory results:
The O & M manuals should contain following minimum information:
On handling over the as-fitted drawings and O&M manuals, a joint site visit shall be arranged with the client’s representative to ensure all works are completed to their satisfaction and obtain a certificate to that extent. Date of this certificate will be the start date of Defects Liability Period.
Indian Plumbing Association (IPA) is the apex body of plumbing professionals in India. Established in 1993 with the objective to promote development of plumbing and building services industry, IPA membership is open to everyone engaged directly or indirectly with the construction industry. Indian Plumbing Association (IPA) has nearly 2000 members, across the country from every segment of the building industry including Consultancy, Manufacturing, Contracting, Trading, Academia and Architecture.
9/3, Chandrashekar Azad Road,
Opp. Gavigangadhara Temple,
Gavipuram, Bangalore- 560 019
Tel; 080-26606963
Fax; 080-26610811
Mob: +91 9901088885
+91 9980799996